Statute of Limitations for Design Professionals
in New York: 3 Years, 6 Years, 10 Years, or
Something Else?
By Steven R. Goldstein, Esq.
*
When an action has been commenced, or is threatened to be commenced,
against a design professional counsel representing the design professional must
promptly evaluate which defenses apply to such claims. Of the many defenses
available to design professionals, asserting the Statute of Limitations defense can result
in a complete dismissal of the lawsuit against the design professional. The Statute of
Limitations, which is the time within which a party must commence an action against
another party, is defined by statute.
Pursuant to the New York Civil Practice Law and Rules, in order to maintain an
action for engineering or architectural malpractice, and/or negligence against a design
professional, the action must be commenced within three years. A claim for negligence
or malpractice against an architect or engineer, arising out of the alleged defective
design or construction of a building, accrues for the purpose of Statute of Limitations
upon the completion of performance of the design professional’s services at the project.
New York Courts look to the date of completion of performance to determine when the
cause of action accrued, no matter whether the claim is characterized as one for
negligence, breach of contract, or fraud. The New York Court of Appeals has defined
completion of performance as completion of the actual physical work, even though
incidental matters may remain. This portion of the statute applies when the design
professional has a contractual relationship with the party claiming damages (privity of
contract). However, when there is no privity of contract, for example when a person
walking by a construction site trips and falls and sustains personal injuries or property
damage, that party has three years to commence the action from the date when the
injury occurs.
Notably, while a design professional may claim that their services were
completed on a particular date, should the design professional be requested to return to
the project to assist in correcting an issue for which the design professional had

*
Steven R. Goldstein, Esq. isthe Principalof GoldsteinLaw, PC, with officesin GardenCity, NY andNew York
City.GLPCprovidesafullrangeoflegalservicestodesignprofessionalsfromriskmanagementthroughtrial.
originally been retained, the "Continuous Treatment" doctrine may be applied to extend
the Statute of Limitations. Specifically, in the event the initial Statute of Limitations has
not yet expired and a design professional returns on a number of dates to address an
issue for which the design professional was retained, the Statute of Limitations accrual
date is extended until the date that the design professional's further association with the
party on that issue is completed.
In addition to the three year Statute of Limitations applicable to design
professionals in New York, a breach of contract claim is often also asserted against the
design professional. The breach of contract Statute of Limitations is six years from the
date of the alleged breach. It is important for the design professional and their counsel
to carefully evaluate the elements supporting the alleged breach of contract claim, as
the courts have often held that the claim is actually one sounding in negligence and
therefore subject to the three year limitations, rather than a breach of contract subject to
a six year Statute of Limitations. In this regard, once the design professional performs
a service, which is claimed by others not to have been properly performed and resulted
in damages, such claims are often viewed by courts as being associated with
negligence, and not breach of contract.
Another issue that is often addressed in evaluating Statute of Limitations is the
Statute of Repose. A Statute of Repose is a statute that cuts off certain legal rights if
they are not acted on by a particular deadline. New York does not have a specific
Statute of Repose with respect to claims asserted against design professionals.
Notwithstanding, the New York legislature modified the existing law by providing
additional elements which must be satisfied should a party seek to pursue a claim
against a design professional more than ten years after the services were performed by
the design professional. To proceed in this manner, the claimant must file a Notice of
Claim prior to the service of a Summons and Complaint. Should the claimant properly
proceed with a Notice of Claim, 90 days thereafter they may pursue a claim against the
design professional. Under such circumstances, in response, the design professional
often proceeds with a motion for summary judgment arguing that there is no substantial
basis in fact and law to establish that the conduct of the design professional was
negligent, and that such conduct was the proximate cause of the claimed damages.
Under the statute, the burden rests on the claimant to establish a substantial basis for
advancing such a claim. This is a rather high threshold and as such, it is a rarity when
such claims are permitted to proceed so far after the design professional's services are
completed at a project.
CONCLUSION
In evaluating the viability of a Statute of Limitations defense, it is incumbent upon
the design professional's counsel to promptly obtain and review all relevant project
records in the design professional's possession. Proceeding in this manner should
provide counsel with information that either supports or refutes the Statute of Limitations
defense. This necessary step early on often results in the design professional obtaining
a voluntary discontinuance or, if necessary, dismissal of the claims against the design
professional. With respect to the Statute of Repose, while it exists and is an avenue for
a claimant to potentially pursue a claim against a design professional, it is one that is
not often pursued based, in part, on the difficult threshold of establishing a substantial
basis for advancing the claim.
Thus, whether or not a viable claim may exist against a design professional
based on the design professional's actions or inactions at a project, immediate and
proper evaluation of the applicable Statute of Limitations may result in prompt dismissal
of such action and, in turn, the inability of the claimant to recover damages against the
design professional for such claims.
This article is for general informational purposes only, does not create an attorney-client
relationship between the reader and author, and is not meant to provide legal advice.
© 2017 Goldstein Law, PC
All Rights Reserved
Attorney Advertising